Spent lots of time haggling over details that should have been done already...but hopefully they really are done now that we have returned to what amounts to the original glass design. Updated lighting plans should be in my hand Monday...if not, I will certainly be ranting on the blog. It looks like fluorescent indirect and task lighting inside, with LED detail lighting outside. Not sure if I am excited about this or not...we will see.
Sunday, December 09, 2007
The Week That Was...
So...I haven't posted much this week. Here is the update:
Steel to support the benches inside and out are in place
Skin and light coves in place outside
framing largely done inside
Demolition on the doorway to the bathroom is complete
Long meeting with the architect and project manager finalizes the design of the glass installation...and maybe the lighting too...
Spent lots of time haggling over details that should have been done already...but hopefully they really are done now that we have returned to what amounts to the original glass design. Updated lighting plans should be in my hand Monday...if not, I will certainly be ranting on the blog. It looks like fluorescent indirect and task lighting inside, with LED detail lighting outside. Not sure if I am excited about this or not...we will see.
Spent lots of time haggling over details that should have been done already...but hopefully they really are done now that we have returned to what amounts to the original glass design. Updated lighting plans should be in my hand Monday...if not, I will certainly be ranting on the blog. It looks like fluorescent indirect and task lighting inside, with LED detail lighting outside. Not sure if I am excited about this or not...we will see.